Sinton Trail Spring Closure

Sinton Closure This Spring for Bridge Demolition

Sinton Trail Closure: Early June – Mid July

UPDATED 7/7/2025: The Sinton Trail was open for Bike To Work day, has reopened Thursday July 3rd, will close Monday July 7th reopening Thursday July 10th. This, most recent closure, is for wall construction of I-25 crossing Ellston Street and the Sinton Trail Connection. For info on other upcoming trail closures visit our Summer Pikes Peak Greenway, Sinton Trail & 8th Street Closures post.

Key Details:

  • UPDATED – Expected Closure Period: June 20 – June 24, June 25 – July 3, July 7 – July 10
  • Reason: Safety during bridge demolition and wall construction for the I-25 Acceleration/Deceleration Lanes Project
  • Bike to Work Day (June 25): Trail will be open
  • Detour Required: Follow posted signs for alternate routes

A Note for Bike Month (June):
We recognize that June is Bike Month, and this closure is especially disruptive for commuters and recreational riders. A special thanks to the project team for coordinating the schedule to ensure the trail for Bike to Work Day (June 25)—helping our community celebrate riding for transportation!

The trail will be closed in late June through July 3 to ensure public safety during the demolition of the Ellston Street Bridge at I-25. Officials expect to reopen the trail on Thursday day, July 3.

The project team understands the inconvenience this closure causes for regular trail users. Respecting the closure will allow the team to complete the project and reopen the trail as quickly as possible. Thank you for your cooperation!

Detour options for bicyclists and pedestrians

  • South on Chestnut Street, crossing I-25 at Centennial Boulevard to reconnect with Pikes Peak Greenway Trail.
  • North on Chestnut Street to Garden of the Gods Road, reconnecting with Pikes Peak Greenway Trail east of Pikeview Reservoir.
  • Garden of the Gods Road to south on Chestnut Street.
  • Filmore to Chestnut Street
Trail Users Detour Map I-25 Accel. Decel. Lanes from Garden of Gods to Fillmore
Trail detour Map – More info available on CDOT website

Be aware there is construction occurring on the West side of the Pikes Peak Greenway north of Uintah and Centennial, to use the Centennial detour will require connecting via the Mesa Springs Greenway (west of I25) or Recreation way

Stay Informed

For the latest updates on the Sinton Trail project, including detour information, please:

Project background

First Bike COS Post about this project
Announcing Construction Start
Announcing Complete Closure
Trail Reopening Announced