Enjoy Repaved Sinton Trail open now
Sinton Trail through Douglas Creek Open Space has reopened
The major repaving project on Sinton Trail which started August 2025 is now complete with a new Concrete trail surface, flattening of uneven pavement, and improvements to drainage and alignment
Keep scrolling to read more info on these , click below to view our interactive detour and closure map.
🛠 Sinton Trail Repaving
(August – November 2025)
The Sinton Trail between Chestnut St. and Holland Park was closed for four months for this project and was funded by voter approved PPRTA 2 funds, City Sinton Trail project website linked here.
Read more on our previous coverage of the Sinton trail project and to see before photos of the trail here – Sinton Trail

Riders enjoying the new concrete Sinton trail 
New concrete Sinton trail with gravel running path 
New concrete Sinton trail 
Trail to Chestnut underpass is paved but no access on east side until I-25 project is complete 
Remnants of the pipe that used to cross Sinton trail 
final concrete being poured before opening of Sinton trail 
West of Holland park will be repaved in a future stormwater project 
Centennial Underpass reconstruction approved by voters as part of PPRTA 3 is still in planning stages
Future Phases:
Holland Park to Centennial – Trail will be addressed during a planned stormwater, timeline depends on FEMA funding.
Centennial to GoG Road – be dependent on funding availability, but likely PPRTA 3 dollars, since other corridors are being addressed.
Douglass Creek drainage work – Work is expected to start in late 2026 to replace the mid trail low water crossing and improve Douglas Creek stability.
We’ll share timelines when available.
Future Future Project: The Centennial Underpass reconstruction approved by voters as part of PPRTA 3 is still in planning stages – more details coming.